Main menu:
Projects Profiles
Project : Huntsman Tioxide High Purity Water Treatment Plant, Teesside
Contract Value : £1.02m
Client : Anglian Water Group
Project Manager : BES Consulting Engineers
Year Completed : 2000
The project comprised the design, fabrication and installation of a Reverse Osmosis water treatment
plant, together with the construction of a purpose built facility to accommodate the plant. The installation was to be installed on an existing hazardous chemical site with all the ensuing requirements of on site control for Health and Safety. The scope of work also included the installation of electrical services and connections to existing live effluent drains.
The building was constructed under a JCT 98 Standard Form of Building Contract, with the process plant being a separate Design and Build Contract using the IChemE Red Book form of contract. The programming of this project was crucial to the Employer, and the site operator was not disrupted in any way during the contract period. Specialist water treatment plant design was undertaken by Anglian Water Group.